|
The main objective of
the revised generation expansion plan is the realisation
of Kapichira Phase II earlier than 2010 in order to
adequately meet the fast growing demand for power within
Malawi, since recent power demand trends with the Southern
Africa Power Pool, from which Malawi intends to tap
power through the Mozambique-Malawi Interconnector,
have shown that the regional interconnected system might
start facing major power shortages by 2007, if the current
stagnation in development of new power generating facilities
within the region continues.
Phase II works will largely
be electromechanical in nature, with minimal civil works,
since most of the civil works (associated with the headrace
tunnel, intake structure, powerhouse and the tailrace)
for the remaining two units were already undertaken
under Phase I. The Project cost is estimated at US$47.0
Million.
In February 2006, ESCOM
signed a contract with Hydel Engineering & Construction
Limited (HECL) for the Repair, Rehabilitation, &
Re-commissioning of Tedzani I&II Power Plant at
a cost US$11.6 Million. Work which will take approximately
14 months to complete is currently progressing well.
ESCOM also intends to incorporate modernization of some
of the power plant & equipment into the project
at an extra cost of US$5.2 Million.

Part of Tedzani Falls I&II Power Station Intake
A Project Proposal for
generation rehabilitation was thus prepared, which mainly
focused on the rehabilitation of electromechanical plant
at Nkula and Tedzani Power Stations (plus existing thermal
power plants in Blantyre, Lilongwe, Mzuzu and Karonga)
and relied solely on additional power from Kapichira
Falls Phase I Hydroelectric Power Scheme and the proposed
interconnection with Mozambique to cushion the impact
that prolonged outage of the stations being rehabilitated
might have on the system.
The Project cost is estimated at US$25.0 Million.
An analysis of the existing
ESCOM generation and transmission system shows that
one of the best was to address the short and medium
term threats to the system is through the provision
of strategic standby power. In this regard, provision
of standby power in the major cities of Blantyre and
Lilongwe, these being the major load centres and strategic
cities to the economy of the country, has been under
serious consideration by ESCOM for the past 3 to 4 years
as the best quick-fix solution available.
ESCOM is currently running
a project to interconnect its power system with the
Southern African Power Pool (SAPP) through interconnection
with Mozambique power system. The Mozambique-Malawi
Interconnector will have a power transfer capacity of
up to 300MW per circuit over a limited time.
The Line will bring into
ESCOM power system improved reliability & security
of power supply and also provide the much needed base
load supply which will enable deferment of more costly
internal generation projects. It will also facilitate
rehabilitation of old/aged hydro power plants.
In September 2004, ESCOM
procured Mechanical Plant worth US$799,950.00 to combat
weed/floating plants problem. The plant, comprising
of an Aquatic Vegetation Cutter (AVC), Harvester, Shore
Conveyer, Workboat, & Boom, operates upstream of
Liwonde Barrage.
The AVC cuts/chops the
weeds/floating plants into small pieces while the Harvester
harvests and, using the Shore Conveyer, loads the chopped
material onto trucks onshore. ESCOM staff were trained
in operations & maintenance of the plant supplied
by Aquarius Systems of USA.
| 
Mats of Aquatic Weeds Floating
on Shire River Upsrteam of Liwonde Barrage
|

The Aquatic Plant Harvester
on Shire River
|
Due to environmental
degradation and bad farming practices in the catchment
area of the Shire River and its tributaries, large quantities
of silt are deposited in ESCOM’s Hydropower Stations’
Reservoirs thereby reducing their live storage capacity.
Silt also accelerates wear of waterways and turbine
parts thereby increasing the operational costs through
frequent utilization of spare parts and power plant
outages.
To reduce the impact of siltation of the Reservoirs,
ESCOM has been carrying out dredging operations at Nkula
Falls Power Stations Reservoir since 1998 when a Dredger
was procured at a cost of MK35.0 Million. There are
plans to procure Dredgers for Tedzani Falls as well
as Kapichira Falls Power Stations in the very near future.

Heavy Silt Deposits at Nkula Falls Power
|

Dredger in Opearation at Nkula Falls Power
|
|