Escom Home News & Media
TEDZANI I and II REPAIRS OVER

Hydel Engineering and Construction Limited (HECL) successfully completed the repair and rehabilitation of Tedzani I and II power stations in August 2009 and handed over the final two all machines to ESCOM for commercial operation.

The development is the completion of the rehabilitation works of Tedzani I and II which has restored the lost 40 megawatts (MW) to the power supply grid, translating into a total available capacity of 278MW against a total demand of about 300MW.

However, there are some defects that need to be cleared by the contractor by November 2009.

Availability of Tedzani I and II will help reduce the load shedding hours.

The power stations got damaged in 2001 because of excessive weeds that accumulated on the Bell mouth fine screens.